KOSS Kindergartens 3 Locations

20 Week Delivery 36 Modules Single Storey 66 Children Capacity
All Projects
Key Challenges
  • Delivering three custom kindergartens across multiple locations in under 5 months
  • Minimising disruption during construction on live school sites
  • Integrating bespoke design and landscaping into a modular solution

Grove has emerged as a key contributor to the Victorian School Building Authority’s (VSBA) Kindergarten on School Site (KOSS) program, which leverages modular construction to fast-track delivery of bespoke early learning environments. As one of the program’s pioneers, Grove was tasked with delivering three turnkey kindergarten facilities across Meadowglen, Newhaven, and Wonthaggi — all within a tight 5-month timeline.

From initial design through to landscaping, Grove managed every element of the project to ensure minimal disruption to the school environments. Each facility was designed around open-plan learning spaces to allow for adaptable classroom configurations and featured integrated, custom-designed playgrounds to promote outdoor engagement.

By prefabricating modules offsite, Grove dramatically reduced on-site time, ensuring the school operations remained uninterrupted and the kindergarten operators could begin programming sooner. This streamlined process improved safety outcomes, lowered costs, and accelerated delivery — all while maintaining exceptional quality standards.

The successful rollout of these kindergartens highlights Grove’s ability to collaborate closely with government stakeholders and demonstrate how modular construction can be both innovative and community-focused.

We were thrilled to be involved in such a new and forward-thinking program. To be able to deliver a high-end product, but remove the normal pains associated with a drawn-out construction process showed the success of the concept.

Brenton Grove – Grove CEO

Explore more

Education
1,904 SQM 3 Stories
Box Hill Primary School
Box Hill, Victoria
Education
2 Days Installation 17 Modules 648 SQM
Sydney Road Community School
Brunswick, Victoria
Education
19 Week Delivery 1,450 SQM 3 Stories 36 Modules
South Yarra Primary School
South Yarra, Victoria